Over 2022-2023 Public Works conducted engagement on the reconstruction of 1st Ave. S from Lake St to Grant St in downtown. This 1.5 mile long corridor was advanced due to the poor pavement condition, multimodal transportation needs, and equity considerations. The current construction on the Lake to Franklin stretch is anticipated to be substantially complete by the end of this year with final touches, including plantings, installed in 2026.
In 2023, due to funding constraints the segment from Franklin to Grant was moved to 2027. Public Works is happy to report that they have been able to advance this work to 2026. Adjacent property owners can expect postcards with details about the public hearing process in the coming weeks.
The approved concept layout can be found here. The newly reconstructed street will feature a two-way protected bike facility, reduced pedestrian crossing distances, greening and green stormwater infrastructure, new signals and signage, and improvements on cross streets with bike facilities, in addition to the benefits of a newly reconstructed pavement surface.
Most details of the project from engagement are housed on the Lake to Franklin website, residents may want to bookmark the Franklin to Grant website for upcoming construction information. Within the coming months a construction engineer will be assigned to the project and that person will be the primary point of contact for questions about debris, noise, or other on-the-ground concerns.
1st Ave S Reconstruction project overview
The Minneapolis Public Works Department plans to reconstruct 1st Ave. S from Lake St. to Franklin Ave., including replacing the Midtown Greenway Bridge. In addition to new pavement, the project will include new sidewalks, an off-street bicycle facility, updated safety features, sanitary and storm main replacement, and green stormwater infrastructure.
Construction update
1st Ave. S closure
Segments of 1st Ave. S will continue to be closed through the fall of 2025. Drivers will need to follow the posted detour route.
Tentatively, starting on Friday, Sept. 26, the work to install the final layer of asphalt between Lake St. and 26th St. E. will begin. This work may last through Tuesday, Sept. 30.
Traffic control update
What to expect
Businesses remain open through construction
As construction continues along 1st Avenue S., businesses remain open.
Upcoming Events
1st Ave. S Reconstruction field hours
Come visit us at our bi-weekly field hours to learn more about construction:
October date TBD
Wesley Andrews Coffee & Tea,111 E 26th St., Minneapolis, MN 55404
Stay connected
Visit the project website; Sign up for project updates: minneapolismn.gov/government/projects/1st-ave-lake-st/
Contact the project engineer: Tracy Lindgren,
tracy.lindgren@minneapolismn.gov or 612-290-5898
Contact the transportation engineer: Abdullahi Abukar,
abdullahi.abukar@minneapolismn.gov or 612-673-2463
Email info@firstavesouth.com
Contact the project hotline with questions, comments or concerns: 612-451-030.
For an overall picture of construction activity throughout Downtown Minneapolis: https://www.minneapolismn.gov/getting-around/parking-driving/road-closures-map/